Client | Project | WorkSummary | Weight(ton) | Duration |
---|---|---|---|---|
Siam Cement Company | Lampang 1 | Fabricate side tripper | 15/7/38 15/4/39 | |
Siam Cement Company | Tung Song 5 | Fabricate side tripper | 15/7/38 15/4/39 | |
Kvaerner ABB Consortium | Bhumibol Hydro Power Project | Install unit 8 spiral draft tubes and associated equipment | 4/7/37 31/12/38 | |
Voest Alpine M.C.E. | Pak Mun Hydroelectric | Fabricate intake trash racks for hydro power plant | 2/5/35 31/3/36 | |
Voest-Alpine M.C.E. | Pak Mun Hydroelectric | Fabricate draft tube for hydropower turbine | 15/11/34 10/4/35 | |
Siam Cement Company | Kao Wong 1 | Fab and erect large fan casing | 20/7/34 15/3/35 |
Registered Office :
215/148-149 Pracharad 1Rd.,
Kwang Bangsue,Khet Bangsue, Bangkok 10800 Thailand Tel.: +66 (0)2 585 2556 to 8 Fax : +66 (0) 2 587 6068 |
VIPCO 2 Main Workshop :
42, 52 Moo 7, Koo-Bang-Luang, Ladlumkaew, Pathumthani 12140 Thailand Tel.: +66 (0) 2 979 4001 to 8 Fax : +66 (0) 2 979 4010 |
VIPCO 1 Workshop :
28/2 Moo 4, Bangkok-Pathumthani Rd., Bang Ka-yang,Muang Pathumthani Pathumthani 12000 Thailand Tel.: +66 (0) 2 975 2811 to 4 Fax : +66 (0) 2 975 2815 |
VIPCO 4 Fin Shop :
220-220/1 Moo 3,Toong Sukhla, Sriracha District, Chonburi 20230 Thailand Tel.: +66 (0) 38 401 207,494 059-60 Fax : +66 (0) 38 401 206 |
VIPCO 5 Workshop :
559/9 Moo. 1 Nong Kham
Sriracha District, Chonburi 20110 Thailand Tel.: +66 (0) 38 110 711-18 |
VIPCO 6 Workshop:
Laem Chabang Port,
(near
CO Seaport), Toong Sukhla, Sriracha District, Chonburi, Thailand |